Alliance Data Center Moratorium

None named yet - Mayor Andy Grove has said at least one company has expressed interest, but no formal proposal or site has been publicly filed · Active - 18-month moratorium in effect, subcommittee doing research toward eventual conditional-use standards

Alliance City Council restricted future data centers to I-2 industrial zones (7-0, mid-June 2026), then passed an 18-month moratorium denying permits for 'AI data centers' citywide (5-1, July 6, 2026, Mastroianni dissenting). A Mastroianni/Cherry-led subcommittee is now researching conditional-use standards, with its first public workshop held Sept 1, 2026. Mayor Andy Grove has said at least one company has already expressed interest in bringing a data center to the city.

Faircrest Data Center (Perry Township)

Panattoni Development Company (California-based); Amazon confirmed by local officials as the operating end user · Under construction. Zoning, tax incentives, and JEDD approvals are complete across all three government bodies involved; the project is now the subject of a September 2026 lawsuit challenging two of those approvals.

Panattoni's 240-megawatt, 100+-acre data center along Faircrest Street SW, with Amazon confirmed by local officials as the operator. Perry Township, Canton, and Stark County all approved a 75%/30-year property tax abatement (Perry gets $2.75M upfront) between March and June 2026. Construction is underway, with about 670 trade workers expected during the build. On September 1, 2026, four residents sued in Stark County Common Pleas Court, alleging Perry Township's noise ordinance and tax-exemption approval both violated Ohio law and the Open Meetings Act - allegations not yet ruled on by any court.

Project Shelby

Panattoni Development Company · Planning/design - not finalized

Panattoni-proposed data center on former Ford Motor Co. industrial land in northeast Canton. Facility size, power capacity, and end user are not yet publicly established; developer held a public open house Aug 18, 2026.